Roscommon Road: Why Good Project Management Made the Difference
When we were approached about the Roscommon Road roof removal and environmental clean, the client had understandable concerns.
Around 12 months earlier, they had experienced significant problems and major cost overruns on a similar-sized project. In our first meeting, the General Manager explained what had happened and wanted reassurance that this project would be different.
My assessment was that the earlier work had lacked dedicated project management. A qualified asbestos removal supervisor had been appointed to run the job, but technical supervision and overall project management carry different responsibilities. A project of this scale needs both.
Planning before work begins
Our approach started with preparation: understanding the site, agreeing responsibilities, planning the sequence of work and coordinating the people involved. Clear expectations from the beginning gave everyone a shared understanding of how the project would run.
Daily management and clear communication
Planning must be followed by active oversight. We maintained a project management presence on site each day, coordinating the crew and engaging directly with the client’s management team and health and safety officers.
That daily involvement kept decisions moving, responsibilities clear and progress aligned with the agreed programme. The client knew who was accountable and had someone available to discuss the work as it progressed.
The result
The Roscommon Road roof removal and environmental clean was completed on time, within budget and without issues.
The difference came from careful preparation, daily project management and consistent communication.
At A1, we believe successful projects begin well before removal starts—and need active management right through to completion.